VOPAK PANAMA ATLANTIC – Vopak New Hose Tower and Pipeline Replacement

VOPAK PANAMA ATLANTIC

EPC for the replacement of the Hose Tower located on the platform of the south pier in Terminal de Bahía Las Minas, Colón Panama, which
serves the terminal for the unloading of fuels from ships of up to 75,000DWT, storage and transfer to other ships. The dismantling of the existing tower and the assembly of the new tower was carried out with maritime equipment.

The project includes the replacement of 12 Oil & Gas product lines, pipes and hoses of different diameters that must be connected and commissioned to the new hose tower. The product pipe lines were transferred using a flotation system and subsequently installed using a crane operating from a Jack-Up barge.

DIPA – Removal of structures and debris of the ACP Oil Crib

DIPA – Dry excavation and dredging works at Agua Clara locks

VOPAK – Demolition Contract – Bahia Las Minas Phase – 1A

Kanan Overseas – Dock System for Energy Barges

IMI | Intercoastal Marine Inc.